Easter Beltie restoration: Week 6

Image by: Susan Cooksleyimg_2419
img_2518
Storm Alex flooded the site, but a week later the water has drained enough to enable works to start again.
img_2443
These narrow dams keep the water in the wetlands separate, ready for removal when it’s time for connection.
img_2453
The priority was to ensure the levels in the chain of the three wetlands were right, so that when the dams are removed the Beltie flows through them in the right order.
img_2390
The level markers that were placed at the start of the works have not been disturbed, showing dig depths across the wetlands.
img_2456
There has been no work on Wetland 4, which isn’t part of the flowing channel, but will take overspill during high flows. Habitat here is already good with snipe regularly spotted in the ditches and pools. It just needs some breaking up to add variety.
img_2495
Wetland 1 can’t be finished until the Beltie has been switched through the wetlands, as the soil that comes out is destined for infilling the old channel.
img_2509-2
Mark Hamblin came back to film the earthworks in the wetlands and conduct interviews with the project team. Thank you to the unsuspecting neighbours who gave up their time to be interviewed.
img_2469
We’ve spotted signs that there have been overnight visitors checking things out. The mud makes it easy to track the badgers and it looks like they are coming down from the hill to visit.
img_2491
This cute visitor tried to win us over, but was kept safely tethered, as the very soft ground and deep water make the freshly-landscaped site hazardous.
img_2419
The wetlands are looking stunning already, and we are itching to see the finished restoration.
img_2520
Looking upstream from the bridge you can see a backwater on the right. Wherever possible we have created pockets of different types of habitat to maximise opportunities for wildlife.
img_2407
Any day now, sea trout and salmon will be moving through on their way to spawn upstream so we always make sure there is a clear route through the system.
img_2513
The outlet channel from Wetland 3 has been roughed out ready for use next week.
img_2503
Weather-allowing these are the last few days that the Beltie will be trapped in this straight trench.
img_2404
Next week we plan to start connecting the Beltie through the wetlands, marking the start of a new and brighter chapter for this part of the burn.

Linked projects:

Easter Beltie restoration